NOTICE: This
opinion is subject to formal revision before publication in the bound volumes
of NLRB decisions. Readers are requested
to notify the Executive Secretary, National Labor Relations Board,
T.E. Briggs Construction Company, Inc. and International
DECISION AND ORDER
By Chairman Battista and Members Schaumber
and Walsh
On April 8, 2004, Administrative Law Judge John J. McCarrick issued the attached decision. The Respondent filed exceptions and a supporting brief, and the General Counsel and the Charging Party each filed an answering brief. The Charging Party also filed cross-exceptions and a supporting brief.
The National Labor Relations Board has delegated its authority in this proceeding to a three-member panel.
The Board has considered the decision and the record in light of the exceptions and briefs and has decided to affirm the judge’s rulings, findings,[1] and conclusions as modified herein, and to adopt the recommended Order as modified and set forth in full below.
i. introduction
The judge found, among other things, that the Respondent, T.E. Briggs Construction Company, Inc., violated Section 8(a)(3) and (1) of the Act by failing to reinstate employee Steven Scheffer, whom the judge found was an unfair labor practice striker, after Scheffer made an unconditional offer to return to work. Specifically, the judge found that the Respondent should have offered Scheffer reinstatement to a laborer position and an equipment operator position, which the judge found were both substantially equivalent to Scheffer’s prestrike position as a pipelayer.[2]
We find it necessary to modify two aspects of these findings. First, although we affirm the judge’s finding that Scheffer engaged in a strike, we find it unnecessary to pass on the judge’s determination that he was an unfair labor practice striker as opposed to an economic striker. Second, although we affirm the judge’s finding that the Respondent unlawfully failed to offer Scheffer reinstatement to a laborer position, we reverse the judge’s finding that the Respondent was required to offer Scheffer an equipment operator position as well. Unlike the judge, we find that the equipment operator position was not substantially equivalent to Scheffer’s prestrike job as a pipelayer. In all other respects, we adopt the judge’s findings.[3]
ii. facts
A. The Respondent’s Operation
The Respondent excavated trenches and installed underground water and sewer pipes in residential subdivisions. To accomplish this work it employed pipelayers, laborers, and equipment operators. Pipelayers used laser levels to set the line and grade of the pipes in the trenches, installed the pipes, and then secured the pipes in the ground. They also performed general work, such as raking, shoveling, and cleaning.
The Respondent’s laborers performed raking, shoveling, and cleaning, and generally assisted the pipelayers. Indeed, pipelayers and laborers frequently worked closely together to install the underground pipes. A laborer often worked as a “top man,” meaning he positioned himself alongside the edge of a trench and provided the pipelayer with any supplies he needed. There is some evidence that pipelayers and laborers earned roughly the same wage rate, in the range of $28 to $29 per hour.
The Respondent’s equipment operators used heavy equipment—backhoes, for example—to dig trenches for the underground pipes, and then used similar equipment to fill the trenches after the pipes were installed. Equipment operators spent most of their working time in the cabs of their equipment; they typically did not work in the trenches. Because of the inherent danger in the equipment operators’ work, they were required to have extensive experience and skill in the smooth operation of the equipment. Equipment operators occasionally helped out with general work, but to a much lesser extent than pipelayers. The record indicates that operators earned a higher wage rate than pipelayers and laborers, in the range of $33 to $34 per hour.
B. Scheffer’s Employment and Strike
The Respondent hired Scheffer as a pipelayer, and he
worked in this position from April 1 until September 10, 2002.[4] As was typical of pipelayers, Scheffer
primarily performed pipelayer work, but he also performed laborer work. He worked for 2 days on a job in
At the time Scheffer was employed by the Respondent, he
was also employed as an organizer for the International Union of Operating
Engineers, Local 302 (
After leaving the Respondent’s jobsite on September 9, Scheffer joined a picket line related to then-pending unfair labor practice charges against the Respondent.[5] Scheffer still reported to work the next day, September 10, as directed by Satterfield. Scheffer received a work assignment for the day, but told Satterfield that he was going on strike until the Respondent remedied its unfair labor practices.
Scheffer remained on strike until November 13. By letter of that date to the Respondent, he made an unconditional offer to return to work. To follow up, Scheffer faxed the same letter to the Respondent in November, and he had the Union place a phone call to the Respondent in December. In 2003, Scheffer made additional unconditional offers to return to work in July, August, September, and October. In late July 2003, the Respondent sent Scheffer a letter informing him that it had no pipe laying work available.
The Respondent, however, did have other work available. In May 2003, the Respondent hired an equipment operator. In June 2003, the Respondent hired a laborer. The Respondent did not offer either position to Scheffer.
iii. discussion
The record fully supports the judge’s finding that Scheffer commenced a strike against the Respondent on September 10. After Foreman Ken Satterfield told Scheffer on September 9 that there was no work for him, Scheffer joined picketers at the Respondent’s office who were protesting the Respondent’s alleged unfair labor practices. The next day, Scheffer appeared at the Respondent’s jobsite and, rather than commence working, he informed Satterfield that he was going on strike. And that is exactly what Scheffer did; he withheld his labor until making an unconditional offer to return to work on November 13. Thus, Scheffer was a striker. See M&M Backhoe Service, 345 NLRB No. 29, slip op. at 10 (2005).
In the circumstances, however, we find it unnecessary to
pass on the judge’s finding that Scheffer was an unfair labor practice striker. The reinstatement rights of an unfair labor
practice striker and an economic striker are the same if the employee has not
been permanently replaced. See Allied Mechanical Services, 341 NLRB
1084, 1085 (2004) (citing Anaheim
Plastics, Inc., 299 NLRB 79 fn. 3 (1990)).
There is no evidence, or claim, that the Respondent permanently replaced
Scheffer. Accordingly, once Scheffer
made an unconditional offer to return to work on November 13, the Respondent
was under a duty to timely reinstate him to his prestrike position or, if that
position no longer existed, to a substantially equivalent position. See NLRB
v. Fleetwood Trailer Co., 389
As there is no claim that Scheffer’s prestrike job as a pipelayer was available, the remaining issue is whether the Respondent was obliged to offer Scheffer the laborer and equipment operator jobs it filled in mid-2003. As indicated, we find that the Respondent’s obligation extended only to the laborer job, as it, unlike the equipment operator job, was substantially equivalent to Scheffer’s pipelayer position.
To determine whether a job is substantially equivalent to
an employee’s prestrike job, “the Board
considers, among other things, the level of responsibility, skill level, wages,
hours, or working conditions of the positions in question.” L.B.&B.
Associates, Inc., 346 NLRB No. 92 slip op. at 3 (2006); Rose Printing Co., supra at 1077–1078. The employee’s qualifications to perform the
job may shed light on whether it is substantially equivalent to his prestrike
job, but mere qualification to perform the job will not suffice. See Rose Printing
Applying these principles, we find that the laborer job was substantially equivalent to Scheffer’s prestrike job as a pipelayer. As described, the Respondent’s pipelayers and laborers worked closely together in and around the trenches installing underground pipes. Pipelayers, unlike laborers, used a laser level to set the line and grade of the pipe, but otherwise they often performed many of the same duties. Further, the record indicates that pipelayers and laborers received roughly the same wage rate. Finally, on at least one occasion the Respondent assigned Scheffer to work exclusively as a laborer, indicating that it considered him qualified to perform such work. All of these facts lead us to conclude that the laborer job was substantially equivalent to Scheffer’s prestrike job as a pipelayer. See, e.g., Zimmerman Plumbing & Heating Co., 334 NLRB 586, 588–589 (2001) (finding substantial equivalency between prestrike and poststrike jobs based on evidence that the jobs were located in the same area, had most of the same duties, involved working with the same materials and tools, and paid approximately the same wage rate).
In contrast, the evidence demonstrates that the equipment operator position was significantly different from Scheffer’s pipelayer position. The equipment operator position involved significantly more responsibility and required greater skill than the pipelayer position. Equipment operators used dangerous heavy equipment to dig and fill trenches. The operators spent most of their working time in the cabs of the equipment; they did not work directly with the underground pipes or in the trenches. Equipment operators were also paid at a higher wage rate than pipelayers, further indicating that the operator job was a more skilled position. Last, although Scheffer occasionally filled in for an equipment operator, there is no evidence that this was a significant part of his job duties. Indeed, the evidence shows that the Respondent did not believe that Scheffer had the requisite experience and skill to operate equipment on a regular basis. For these reasons, we conclude that the equipment operator position was not substantially equivalent to Scheffer’s prestrike pipelayer position. See, e.g., Diamond Walnut Growers, 340 NLRB 1129, 1131 (2003) (finding that a mechanic position was not substantially equivalent to a lead mechanic position where the latter involved significantly more responsibility and required more skills).
Thus, we affirm the judge’s finding that the Respondent violated Section 8(a)(3) and (1) by failing to offer Scheffer reinstatement to the laborer position, but we reverse the judge’s finding as to the equipment operator position.[7]
ORDER
The National Labor Relations
Board adopts the recommended Order of the administrative law judge as modified
and set forth in full below and orders that the Respondent, T.E. Briggs
Construction Company, Inc.,
1. Cease and desist from
(a) Failing and refusing to reinstate strikers, who have unconditionally offered to return to work, to available substantially equivalent positions, where their former positions no longer exist.
(b) Threatening not to rehire
employees because of their union activities.
(c) Threatening employees with
physical harm because of their union activities.
(d) In any like or related
manner interfering with, restraining, or coercing employees in the exercise of
the rights guaranteed them by Section 7 of the Act.
2. Take the following affirmative
action necessary to effectuate the policies of the Act.
(a) Within 14 days from the date
of this Order, offer former striker Steven Scheffer full reinstatement to the laborer
position that became available in June 2003, without prejudice to his seniority
or any other rights or privileges previously enjoyed.
(b) Make Steven Scheffer whole
for any loss of earnings and other benefits suffered as a result of the Respondent’s
refusal to reinstate him to the laborer position that became available in June
2003, with backpay and interest thereon to be computed in the manner set forth
in the remedy section of the judge’s decision.
(c) Within 14 days from the date
of this Order, remove from its files any reference to the unlawful refusal to
reinstate Steven Scheffer and, within 3 days thereafter, notify him in writing
that this has been done and that the refusal to reinstate him will not be used
against him in any way.
(d) Preserve and, within 14 days
of a request, or such additional time as the Regional Director may allow for
good cause shown, provide at a reasonable place designated by the Board or its
agents, all payroll records, social security payment records, timecards,
personnel records and papers, and all other records, including an electronic
copy of such records if stored in electronic form, necessary to analyze the
amount of backpay due under the terms of this Order.
(e) Within 14 days after service by the
Region, post at its facility in
(f) Within 21 days after service
by the Region, file with the Regional Director a sworn certification of a responsible
official on a form provided by the Region attesting to the steps that the
Respondent has taken to comply.
It is
further ordered that the complaint is
dismissed insofar as it alleges violations of the Act not specifically found.
Dated,
|
Robert J. Battista, |
Chairman |
|
|
|
|
|
|
|
Peter C. Schaumber, |
Member |
|
|
|
|
|
|
|
Dennis P. Walsh, |
Member |
|
|
|
|
|
|
(Seal) National Labor Relations Board
APPENDIX
Notice To Employees
Posted by Order
of the
National Labor Relations
Board
An Agency of the
The National Labor Relations Board has found that we violated Federal labor law and has ordered us to post and obey this notice.
federal law gives you the right to
Form, join, or assist a union
Choose representatives to bargain with us on your behalf
Act together with other employees for your benefit and protection
Choose not to engage in any of these protected activities.
We will not fail and refuse to reinstate strikers, who have unconditionally offered to return to work, to available substantially equivalent positions, where their former positions no longer exist.
We
will not threaten not to rehire employees because
of their union activities.
We
will not threaten employees with physical harm
because of their union activities.
We
will not in any like or related manner
interfere with, restrain, or coerce you in the exercise of the rights guaranteed
you by Section 7 of the Act.
We will, within 14 days from the date of the Board’s Order, offer former striker Steven Scheffer full reinstatement to the laborer position that became available in June 2003, without prejudice to his seniority or any other rights or privileges previously enjoyed.
We will make Steven Scheffer whole for any loss of earnings and other benefits suffered as a result of our refusal to reinstate him to the laborer position that became available in June 2003, with interest.
We
will, within 14 days from the date of the
Board’s Order, remove from our files any reference to the unlawful refusal to
reinstate Steven Scheffer and we will,
within 3 days thereafter, notify him in writing that this has been done and
that the refusal to reinstate him will not be used against him in any way.
T.E. Briggs Construction Company, Inc.
Martin M. Eskenazi, Esq., for the General Counsel.
Aaron A. Roblan, Esq. (Jackson Lewis, LLP), of
David Hannah, Esq. (Cedar River Law Professionals,
PLLC), of
DECISION
Statement of the Case
John J. McCarrick, Administrative
Law Judge. This case was tried in Seattle, Washington, on December 16–18, 2003,
upon General Counsel’s amended consolidated complaint1
that alleged T.E. Briggs Construction Company, Inc. (Respondent) violated
Section 8(a)(1) and (3) of the Act by telling an employee that he would not be
rehired because he was Union, by threatening an employee by lifting a rock and
appearing to throw it at him because of the employee’s union activity, by
refusing to offer reinstatement to Steve Scheffer, by disparately treating union
job applicants, and by failing to hire or consider for hire Tom Stuart, Tom
Kennedy, Mark Sandy, Henry Arnoux, Ron Dahl, Dan Taylor, and Daren Konopaski
because of their union activity.
Respondent timely denied any wrongdoing.
On the entire record, including my observation of the demeanor of the
witnesses, and after considering the briefs filed by the parties, I make the
following
Findings of Fact
i. jurisdiction
Respondent,
a
ii. the issues
1.
Did Respondent violate Section 8(a)(1) of the Act by:
a.
Telling an employee that he would not be rehired because he was union?
b.
Threatening an employee by lifting a rock and appearing to throw it at him
because of the employee’s union activity?
2.
Did Respondent violate Section 8(a)(1) and (3) of the Act by refusing to offer
reinstatement to Steve Scheffer, by disparately treating union job applicants
and by failing to hire or consider for hire Tom Stuart, Tom Kennedy, Mark
Sandy, Henry Arnoux, Ron Dahl, Dan Taylor, and Daren Konopaski because of their
union activity?
iii. alleged unfair labor practices
A. The Facts
1. Introduction
Respondent
is an underground utility contractor. In
the course of its business, Respondent excavates trenches and installs main
line pipe, storm and water pipe, and sewers into trenches in residential
subdivisions. Respondent employs
pipe-layers, operators and laborers. Pipelayers set the line and grade for pipe
that is put into trenches. Operators run
the equipment that dig trenches.
Laborers perform a multitude of functions, including cleaning catch
basins, raking and shoveling, picking up garbage, and supporting the pipe
laying operation. The record reflects that there is much cross over among the
job duties of pipelayers, operators, and laborers. Tracy Briggs (Briggs) is the owner and
president of Respondent. Ronald Smith
(Smith) is Respondent’s superintendent of construction. Douglas Ross (Ross) is Respondent’s project
manager. Cody Walker (
2. The refusal to rehire
Steven Scheffer
Steven
Scheffer (Scheffer) was employed by Respondent as a pipelayer, equipment operator,
and laborer from April 1 through September 10, 2002.3
Scheffer was also an organizer for the
On
April 25, Scheffer was working at Respondent’s
On
July 18, Scheffer was working at Respondent’s Vineyard jobsite. At about 6:45 a.m., Amir Gadiwalla
(Gadiwalla), a person of East Indian descent and the director of organizing for
the Union, spoke to Respondent’s employees about the
On
August 9, during the 10 a.m. coffeebreak on Respondent’s Sunlit jobsite,
Scheffer was talking to Respondent’s employees Ford and Ryan about wages and
working conditions under the union contract.
Satterfield came up and told Scheffer he was not allowed to talk about
the
On
August 13 at the Sunlit project near the end of the day, Satterfield told
Scheffer that he could no longer drive the company truck to and from the jobsite. Scheffer had been driving the company truck
on a daily basis prior to this time.
When Scheffer asked if this had anything to do with his union activities,
Satterfield responded, “You stirred the pot, Steve. You and I both know what it’s about.”
On
September 6 at about 1:30 p.m. on the Sunlit jobsite, Satterfield told Scheffer
that there was no more work for him on the job that day but the rest of the
crew would be working. Scheffer watched
the crew work for over an hour doing curb grade, work that Scheffer had done in
the past.
On
September 9, Scheffer went to the Sunlit jobsite but was told by Satterfield
that there was no work for him although the rest of the crew would be
working. Scheffer was told to report to
the Sunlit jobsite on September 10.
Scheffer left the Sunlit jobsite and went to Respondent’s office where
he participated in an unfair labor practice strike and walked a picket line.
The picket signs stated that Respondent violated Federal law and had committed
unfair labor practices.6
On
September 10, Scheffer reported to the Sunlit job at 7 a.m. and told
Satterfield he was going out on strike until the unfair labor practices had
been remedied.
Scheffer
remained on strike until November 13 when he made an unconditional offer to
return to work in a letter of November 13.7 On November 22, a copy of the November 13
letter was faxed to Respondent.8 On December 3, Gadiwalla called Respondent’s
office and advised a clerk to bring to Brigg’s attention that Scheffer had made
an unconditional offer to return to work.
Scheffer made additional offers to return to work on July 18, August 4,
September 4, and October 15, 2003. On
July 21, 2003, Scheffer received a letter from Respondent that advised there
was no pipe laying work available.[9]
In
late May or early June 2003, Respondent hired Jim Miller (Miller) as a laborer
and Charles McJunkin (McJunkin) as an operator.
In January or February 2003, Briggs first spoke to McJunkin at a
jobsite. Respondent had previously
worked at this jobsite and there were issues about Respondent’s placement of
fill. McJunkin was the operator at that
site, working for another employer. In
resolving the issue of Respondent’s placement of the fill, Briggs observed
McJunkin operating equipment at the site. McJunkin asked Briggs if he was
hiring and Briggs said no. Later in
March or April, McJunkin again approached Briggs and gave him his phone
number. Briggs first considered McJunkin
for hire in May 2003. Miller was hired
in June 2003 after he approached Respondent’s superintendent, Ron Smith about a
job.
3. The February 11 and March
14, 2003 refusal to allow Scheffer and Tom Stuart to apply for work
On
February 11, 2003, Scheffer and union member Tom Stuart (Stuart) went to
Respondent’s
On
March 14, 2003, Todd Werner (Werner), an unemployed union member, went with
Scheffer and Stuart to Respondent’s office in
On
March 14, 2003, after Werner’s visit, Scheffer and Stuart went to Respondent’s
4. The June 6, 2003 refusal to hire or consider for hire Tom
Kennedy, Mark Sande, Henry Arnoux, Ron Dahl,
Dan Taylor, and Daren Konopaski
On
June 6, 2003, Union Organizer Todd Hassing (Hassing) went to Respondent’s
Meanwhile,
on June 6, 2003, Scheffer, Tom Kennedy (Kennedy), Mark Sande (Sande), Henry Arnoux
(Arnoux), Ron Dahl (Dahl), Dan Taylor (
On
June 12, 2003, Janet McKinney (
5. The July 7, 2003 statement that Scheffer would
not be rehired because he was union and
the threat to throw a rock at Scheffer
On
July 7, 2003, Scheffer went to Respondent’s
B. The Discussion
1. The alleged 8(a)(1) conduct[14]
General
Counsel has alleged that Respondent violated Section 8(a)(1) of the Act by
threatening not to rehire Scheffer because of his union activity and by
threatening him with physical violence because of his union sympathy.
It is well
established that an employer who threatens not to hire or rehire an employee
due to union activity violates the Act. Structural
Finishing, Inc., 284 NLRB 981, 982 (1987); Starco, Inc., 323 NLRB 977 (1997); and Industrial Construction Services, 323 NLRB 1037, 1039 (1997). Here, on July 7, 2003, Respondent, through
Superintendent Ross, told Scheffer he would not be rehired because he was
union. This statement violated Section
8(a)(1) of the Act.
It
is also the case that an employer who threatens employees with physical
violence violates the Act. The Board
found an employer who threatened to throw rocks at a union organizer violated
Section 8(a)(1) of the Act. Zarcon, Inc., 340 NLRB 1222, 1228
(2003). On July 7, 2003, at the same
jobsite where Ross told Scheffer he would never be rehired because he was union,
Ross picked up a rock and made a throwing motion in Scheffer’s direction. Like the threat to throw rocks in Zarcon,
Ross’ feigning to throw a rock at Scheffer was a threat of physical violence
and came on the heels of his statement that Respondent would not rehire
Scheffer because he was union. Ross’
action violated Section 8(a)(1) of the Act.
2. The refusal to offer
reinstatement to Scheffer
Counsel
for the General Counsel contends that Respondent violated Section 8(a)(1) and
(3) of the Act by refusing to offer Scheffer reinstatement after he made an
unconditional offer to return to work from an unfair labor practice
strike. Respondent counters that
Scheffer was not an unfair labor practice striker since he gave no reasons to
indicate he was an unfair labor practice striker, that Scheffer abandoned his
employment with Respondent by accepting regular and substantial equivalent employment
elsewhere, and that there was no available work for Scheffer to perform upon
his offer to return to work.
It is
settled that both economic strikers and unfair labor practice strikers retain
their status as “employees” under Section 2(3) of the Act. See NLRB v.
Mackay Radio & Telegraph Co., 304
In Zimmerman Plumbing & Heating Co., 339
NLRB 1302, 1304 (2003), the Board held that a former striker who makes an
unconditional offer to return to work must be reinstated to substantially
equivalent positions and to any non-equivalent positions requested for which he
may be qualified.
Scheffer
made unconditional offers to return to work on November 13 and 22 and December 3, 2002, as well as
on July 18, August 4, September 4, and October 15, 2003.
The record reflects that Scheffer was hired by Respondent as a pipelayer. During the course of his employment with Respondent,
however, Scheffer performed other duties including equipment operation and
laborer’s work. Concerning Scheffer’s
duties working on pipe laying crews, Superintendant Ross said Scheffer was a
pipelayer/laborer. Ross said a laborer
and pipelayer, “basically have the same multiple tasks. Labor work could be-a Laborer and a Pipe
layer do a lot of the same things. A Laborer
may use a shovel and a broom. A Pipe
layer will use a shovel and a broom with other tasks, too, to go with it.”[15] Respondent asserts that Scheffer said he
considered laborer’s work below him.
However, there is no evidence he ever refused to perform such work or
that he indicated he would not perform such work upon reinstatement.
There is also evidence that Scheffer frequently operated
equipment.[16] The record is replete with evidence of
Scheffer’s operation of many types of heavy machines. Other than one occasion when Briggs told
Scheffer not to strike the ground so hard with the bucket of the backhoe,[17]
Scheffer regularly received compliments from his supervisors for the quality of
his operator work. Scheffer was told by
Supervisor Leedy he should be operating equipment full time for
Respondent. Briggs assertion that
Scheffer was not qualified to operate machinery is without support in the
record.
Respondent filled the positions of operator and laborer in late
May 2003 after Scheffer made an unconditional offer to return to work. These are substantially equivalent positions
for which Scheffer was qualified.
Moreover, there is considerable evidence that antiunion animus
motivated Respondent’s failure to offer Scheffer reinstatement. Briggs interrogated employees about their
union membership, Satterfield told employees if they wanted to be union they
should work for a union company, Satterfield said he was trained to kill people
like Union Director of Organizing Gaddiwalla, Satterfield told Scheffer he
could not have union literature on the jobsite, Satterfield told Scheffer he
could not operate Respondent’s equipment because of his union activity ,and
Ross told Scheffer he would not be rehired because he was Union and threatened
Scheffer with a rock.
Unless
Respondent can establish a legitimate and substantial business justification
for failing to reinstate Scheffer after November 13, 2002, to an available job
for which he was qualified, General Counsel has established Respondent has
violated Section 8(a)(1) and (3) of the Act.
In its defense, Respondent argues that 3D Enterprises Contracting Corp., 334 NLRB 57 (2001), provides guidance
for the proposition that Scheffer was not an unfair labor practice striker
since he did not give reasons for going on strike. I note initially that the judge in 3D Enterprises Contracting found that
there were no underlying unfair labor practices to give rise to an unfair labor
practice strike. Thus, the remainder of
his decision regarding intent is dicta.
The judge found further that there was no evidence of employees’ intent
concerning the purpose of the strike, as expressed at the time it
occurred:
The
requirement that the General Counsel introduce evidence of employees’
expressions “at the time of the relevant events” is a minimal one, especially
since employer representatives are seldom present when such expressions are
made. Except for the testimonies of Montoney and
Huff about what happened before and after the June 2 union meeting, however,
the General Counsel offered only the type of evidence that the Board rejected
in [Thorpe]—the employees’ “subjective
reasons for striking, as asserted for the first time at the hearing.”[18]
Respondent’s
reliance on 3D Enterprises Contracting is misplaced. Here, there is
evidence of Scheffer’s intent as expressed at the time of the relevant
events. On September 10,
Scheffer reported to the Sunlit job at 7 a.m. and told his supervisor,
Satterfield, he was going out on strike until the unfair labor practices had
been remedied. The previous day,
Scheffer had walked a picket line in front of Respondent’s office where picket
signs were displayed stating that Respondent violated Federal law and had
committed unfair labor practices. Scheffer need not provide a
reasoned explanation for actions. The
only requirement is evidence of employees’ expressions at the time of the
relevant events. Here, Scheffer put Respondent on notice that he was going on
strike to protest unfair labor practices.
I find that Scheffer was an unfair labor practice striker as of September
10, 2002.
Respondent takes the position that Scheffer abandoned his right to
reinstatement by Respondent.[19] The Board has held in Zimmerman Plumbing & Heating Co., 334 NLRB 586, 588 (2001) (Zimmerman I) that:
A
former striker awaiting reinstatement may accept interim employment elsewhere.
Indeed, the Board has recognized that the right to seek interim employment is a
vital adjunct to the exercise of the right to strike and is itself protected
activity. See Christie Electric Corp., 284 NLRB 740, 759 (1987).
Accepting interim employment normally will have no effect on a former striker’s
reinstatement rights. One exception is that if a former striker accepts other
“regular and substantially equivalent employment,” within the meaning of
Section 2(3), then he forgoes his reinstatement rights with the employer. See Marchese
Metal Industries, 313 NLRB at 1028–1031 (1994); Little Rock Airmotive,
Inc., 182 NLRB 666, 667 (1970), enfd. in pertinent part 455 F.2d 163 (8th
Cir. 1972).
….
Determining
whether a former striker’s interim employment constitutes “regular and
substantially equivalent employment” cannot be answered by a “mechanistic application
of the literal language of the statute.”
After remanding the case to the judge, in Zimmerman Plumbing & Heating Co., 339 NLRB 1302 (2003) (Zimmerman II), the Board affirmed the judge who found that employee O’Brien had
not abandoned his employment by taking interim employment elsewhere, noting
that O’Brien, despite his higher paying and substantially equivalent interim
employment, had continued to express interest in his employment with the respondent.
Finally, Respondent contends
that after November 13 there was no available work for which Scheffer was qualified. While Respondent admits that in late May or
early June 2003, it hired Miller as a laborer and McJunkin as an operator, it
argues that Scheffer was underqualifed to be an operator and had expressed no
desire to work as a laborer. As noted
above, I have found Scheffer was qualified to perform work as both an operator
and laborer.
I find Respondent’s failure to reinstate Scheffer was motivated by
his union activity and violated Section 8(a)(1) and (3) of the Act.
3. The failure to hire or
consider for hire the union applicants
Counsel for the General Counsel argues that Respondent discriminatorily
failed to hire and failed to consider union applicants for hire on February 11,
March 14, and June 6, 2003. Respondent
takes the position that it did not violate the Act since the union applicants’ conduct removed them from the protection of
the Act, there is no evidence that they were qualified to fill available
positions, Respondent was not hiring at the time they applied, there is no
evidence antiunion animus motivated Respondent and its nondiscriminatory hiring
policy would have precluded the union
applicants from being considered for hire.
In
(1)
[T]hat the respondent was hiring, or had concrete plans to hire, at the time of
the alleged unlawful conduct; (2) that the applicants had experience or
training relevant to the announced or generally known requirements of the
positions for hire, or in the alternative, that the employer has not adhered
uniformly to such requirements, or that the requirements were themselves
pretextual or were applied as a pretext for discrimination; and (3) that
antiunion animus contributed to the decision not to hire the applicants. Once this is established, the burden will
shift to the respondent to show that it would not have hired the applicants
even in the absence of their union activity or affiliation. [
The
employer has the burden of proof to show that the applicant did not meet its
criteria for the position, was unqualified for the position or was not as
qualified as others who were hired.
In
refusal to consider for hire cases the Board in
To
establish a discriminatory refusal to consider, pursuant to Wright Line, supra, the General Counsel
bears the burden of showing the following at the hearing on the merits: (1) that
the respondent excluded applicants from a hiring process; and (2) that
antiunion animus contributed to the decision not to consider the applicants for
employment. Once this is established, the burden will shift to the respondent
to show that it would not have considered the applicants even in the absence of
their union activity or affiliation. [
a. Tom Stuart
Counsel for the General Counsel argues that Respondent both failed
to hire and failed to consider Stuart for hire.
On February 11 and March 14, 2003, Stuart attempted to apply with
Respondent for a position as an operator.
While there is no doubt that Stuart was a qualified operator, there is
insufficient evidence that Respondent was hiring or had concrete plans to hire any
operators in February or March 2003. Counsel
for the General Counsel argues that Respondent was considering McJunkin for
hire during the January to March 2003 period.
However, the record reflects that it was McJunkin who was lobbying for a
job with Respondent and until mid-May Briggs consistently told McJunkin
Respondent was not hiring. I find that
General Counsel has failed to establish a prima facie case that Respondent
discriminatorily refused to hire Stuart since there is no evidence Respondent was
hiring or had concrete plans to hire on February 11 or March 14, 2003.
With respect to the allegation that Respondent failed to consider
Stuart for hire, there is some evidence that Respondent gave nonunion
applicants greater access to Respondent’s office than union applicants. Counsel for the General Counsel argues
nonunion identified applicants Werner, Hassing, and
When Stuart and Scheffer approached Respondent’s office on
February 11, 2003, wearing union insignia, the
door was locked. When Stuart and
Scheffer went to Respondent’s office on March 14, 2003, wearing union insignia they were told by